Manston airport: now the DCO is set to be quashed

Elementary Admin
By Elementary Admin &
7th December 2020

Manston… here we go again

Well, it was never going to go smoothly, was it!
The granting of a Development Consent Order allowing developer RiverOak Strategic Partners to reopen Manston airport as a freight hub is to be quashed.
The Department for Transport has accepted that the DCO approval letter from Andrew Stephenson, Minister of State for Transport, did not contain enough detail on why the conclusions of the four-man Planning Inspectorate’s Examining Authority were effectively dismissed.
The Examining Authority had been clear that the DCO should not be granted.
It is understood that its approval will be quashed within three weeks, with a revised decision needed after the Planning Inspectorate evidence is re-examined.
The likely revocation of the DCO means a judicial review of Mr Stephenson’s decision scheduled for Tuesday and Wednesday, February 16-17, at the High Court will not now go ahead.
The review had been launched by Jenny Dawes, chair of Ramsgate Coastal Community Team.  
However, on Wednesday last week (December 2), she wrote on her CrowdJustice page set up to help fund the judicial review: “… yesterday my solicitors received a letter from the Treasury Solicitor, acting on behalf of the Secretary of State for Transport, which said ‘my client has agreed to concede this claim on the basis of ground 1(b), namely that the Secretary of State did not give adequate reasons in his decision letter to enable the reader to understand why he disagreed with the Examining Authority Report on the issue of need for the development of Manston Airport’. 
“We subsequently learned that the Interested Party, RiverOak Strategic Partners Ltd, will not be defending their claim.
“My lawyers set out three grounds of challenge to the decision to grant a Development Consent Order for the re-opening and development of Manston Airport:
Ground 1: Need
Ground 2: Breach of Procedural Requirement/Unfairness
Ground 3: Net Zero Duty”
Two days later, Friday (December 4), Ms Dawes added: “Following the quashing of the Manston Airport Development Consent Order 2020 by the Court, the Secretary of State will write to all interested parties, setting out key issues and inviting further written representations on those issues.
“Interested parties include the applicant, the local authority and anyone who previously registered by filling out a Relevant Representation form at the inquiry stage (and had it accepted as valid).
“The Secretary of State will make a decision based on the Examining Authority’s Report and the further representations. The Secretary of State has three months to make a decision but this can be extended.
“The decision could be either a refusal to make a Manston Airport Development Consent Order or a decision to grant such a Consent Order.
“If a DCO is refused, RSP may wish to bring a judicial review. I would be an Interested Party in any such challenge.
“If a DCO is granted, another judicial review can be brought on the existing grounds and any further grounds that may arise on review of the decision letter.
“Any money left over from the current CrowdJustice campaign can be held in readiness and used towards a second judicial review.”
At the time of writing, that campaign had seen more than £88,000 pledged towards the initial review.
Responding in July to the news of the DCO approval, Hilary Newport, CPRE Kent director, had said: “It is shocking that four inspectors spent some nine months preparing a report and concluded very strongly that the DCO should be refused.
“The developer was not able to demonstrate need, there were adverse impacts on traffic and transport and there were concerns over noise pollution.
“Most importantly, though, the Examining Authority recommended the Secretary of State refuse the DCO due to conservation of habitats and species regulations.
“In short, the inspectors’ conclusions were ignored.
“This decision flies in the face of the Heathrow third-runway judgement where the Court of Appeal ruled that proposals had failed to consider this country’s commitment to reduce carbon emissions.”
Although the Manston decision had to be made in the name of Grant Shapps, Secretary of State for Transport, the DfT said Mr Shapps had “not personally been involved in this decision because of a conflict of interest, following previous statements of support made prior to his appointment as the Secretary of State for Transport” and the decision had “in practice been allocated to and taken by the Minister of State for Transport, Andrew Stephenson”.

  • For more on Manston airport, see here

Monday, December 7, 2020


  • A number of important documents have yet to emerge. For example, a rigorous transport plan and a finalised air-quality assessment. The latter is critical given that allocations at Teynham will feed extra traffic into AQMAs.
  • There seems to be no coherent plan for infrastructure delivery – a key component of the plan given the allocations being proposed near the already crowded Junction 7.
  • There seems to have been little or no cooperation with neighbouring boroughs or even parish councils within Swale itself.

The removal of a second consultation might have been understandable if this final version of the plan were similar to that being talked about at the beginning of the consultation process. It is, however, radically different in the following ways:

  • There has been a major shift in the balance of housing allocations, away from the west of the borough over to the east, especially around the historic town of Faversham. This is a move that raises many concerns.
  • A new large allocation, with accompanying A2 bypass, has appeared around Teynham and Lynsted, to which we are objecting.
  • Housing allocations in the AONB around Neames Forstal that were judged “unsuitable” by the council’s own officers have now appeared as part of the housing numbers.
  • Most of the housing allocations being proposed are on greenfield sites, many of them on Grade 1 agricultural land – a point to which we are strongly objecting.

Concerns about the rush to submit the plan

The haste with which the plan is being prepared is especially worrying given the concentration of housing in Faversham. If the town is to take a large amount of new housing, it is imperative that the policies concerning the area are carefully worked out to preserve, as far as possible, the unique nature of the town. The rush to submit the plan is likely to prove detrimental.

As Swale does not have a five-year land housing supply, it is open to speculative development proposals, many of which would run counter to the ideas contained in the current plan. Some are already appearing. This is a common situation, and one that, doubtless, is a reason behind Swale’s haste.

Our overriding fear, however, is that this emphasis on haste is ultimately going to prove counterproductive. This is because it is our view that the plan, in its current form, is unlikely to pass independent examination. We are urging Swale to listen to and act upon the comments being made about the plan and to return the plan to the council with appropriate modifications before submitting it to the Secretary of State.

Essentially, this means treating the current consultation not as the final one but as the ‘lost’ second consultation.

The consultation ends on Friday 30 April and we strongly urge residents to make their opinions known if they have not already done so.

Further information