Cleve Hill, plans for the UK's largest solar farm... and our response

Elementary Admin
By Elementary Admin &
13th July 2018
The special landscape of Graveney Marshes would be destroyed if the Cleve Hill solar park was approved (picture by Vicky Ellis)

The damaging proposal for the country’s largest solar farm, at Cleve Hill near Faversham, has reached the second public consultation phase and CPRE has taken the opportunity to clarify its strong opposition to the project.
Our response totals almost 1,700 words, but our primary concerns lie in the following areas (more may be added after scrutiny of the Development Consent Order application):

  • Damage to landscape including tranquillity and dark skies
  • Inadequate assessment of flood risk and potential conflict with the Environment Agency’s ‘managed retreat’ strategy
  • Impacts on soil microclimate and hydrology
  • Ecological impacts
  • Damage to heritage assets caused by construction traffic
  • Loss of agricultural land
  • Threats to animal welfare

CPRE Kent recognises the challenges of climate change and the government’s commitment to meeting carbon emission targets but does not consider the renewable-energy benefits of the scheme proposed by developers Hive Energy and Wirsol – which has already grown from an initial 890 acres to 1,000 – outweigh the damage it would cause the North Kent Marshes.
We also question the sustainability of reliance on lithium-ion technology, with its own remote but concerning ecological impacts.
In short, the solar farm proposal is on a wholly unacceptable scale and in entirely the wrong location; it carries a disturbing catalogue of harmful impacts and it is to be hoped that the plans are ultimately stopped in their tracks.
Read our response to the consultation: Cleve Hill II Consultation Response (CPRE)

  • A number of important documents have yet to emerge. For example, a rigorous transport plan and a finalised air-quality assessment. The latter is critical given that allocations at Teynham will feed extra traffic into AQMAs.
  • There seems to be no coherent plan for infrastructure delivery – a key component of the plan given the allocations being proposed near the already crowded Junction 7.
  • There seems to have been little or no cooperation with neighbouring boroughs or even parish councils within Swale itself.

The removal of a second consultation might have been understandable if this final version of the plan were similar to that being talked about at the beginning of the consultation process. It is, however, radically different in the following ways:

  • There has been a major shift in the balance of housing allocations, away from the west of the borough over to the east, especially around the historic town of Faversham. This is a move that raises many concerns.
  • A new large allocation, with accompanying A2 bypass, has appeared around Teynham and Lynsted, to which we are objecting.
  • Housing allocations in the AONB around Neames Forstal that were judged “unsuitable” by the council’s own officers have now appeared as part of the housing numbers.
  • Most of the housing allocations being proposed are on greenfield sites, many of them on Grade 1 agricultural land – a point to which we are strongly objecting.

Concerns about the rush to submit the plan

The haste with which the plan is being prepared is especially worrying given the concentration of housing in Faversham. If the town is to take a large amount of new housing, it is imperative that the policies concerning the area are carefully worked out to preserve, as far as possible, the unique nature of the town. The rush to submit the plan is likely to prove detrimental.

As Swale does not have a five-year land housing supply, it is open to speculative development proposals, many of which would run counter to the ideas contained in the current plan. Some are already appearing. This is a common situation, and one that, doubtless, is a reason behind Swale’s haste.

Our overriding fear, however, is that this emphasis on haste is ultimately going to prove counterproductive. This is because it is our view that the plan, in its current form, is unlikely to pass independent examination. We are urging Swale to listen to and act upon the comments being made about the plan and to return the plan to the council with appropriate modifications before submitting it to the Secretary of State.

Essentially, this means treating the current consultation not as the final one but as the ‘lost’ second consultation.

The consultation ends on Friday 30 April and we strongly urge residents to make their opinions known if they have not already done so.

Further information