Lower Thames Crossing… the saga rumbles on

We reported last week that Highways England had withdrawn its application for a Development Consent Order to build the Lower Thames Crossing.
Now we have been updated by HE on the issues relating to the Planning Inspectorate and the likely way forward.
A message to  stakeholders said: “… we’ve now had further dialogue with the Planning Inspectorate about their expectations around our application.
“The fundamentals of the Lower Thames Crossing, including its objectives and location, will remain the same but we will further develop some technical information related to some elements of the scheme before we resubmit our application next year.
“The feedback from the Planning Inspectorate includes requests for:
“Further information on the impact of the project on traffic during the construction phase. We recognise that stakeholders are keen to find out more information about our construction traffic appraisals and will be engaging with them on these issues.
“Further assessments about how an existing jetty on the River Thames near the northern tunnel entrance construction site could potentially be used during the construction phase. The operation of the jetty could, if used, impact river traffic. We will be developing Navigational Impact Assessment and engaging with stakeholders on this topic.
“More details on our approach for managing materials and waste, including how the different contractors will coordinate the reusing, recycling or disposal of waste.  
“An enhanced Habitats Regulations Assessment to provide a more detailed explanation of our approach to assessment of potential effects on European designated sites where we have indicated there would be no likely significant effects as a result of the construction and operation of the new road alone, or in combination with other projects.
“More detail on our approach to the long-term management of the project’s proposed environmental mitigation.
“The Planning Inspectorate has also shared some feedback from Local Authorities on our approach to consultation. We will consider this feedback carefully as we refine key areas of our submission ahead of resubmitting our application for a Development Consent Order.
“For a project of the size and complexity of the Lower Thames Crossing, it is reasonable for the Planning Inspectorate to ask for further information, and we are doing everything we can to resubmit our application at the earliest opportunity.”

Friday, November 27, 2020


  • A number of important documents have yet to emerge. For example, a rigorous transport plan and a finalised air-quality assessment. The latter is critical given that allocations at Teynham will feed extra traffic into AQMAs.
  • There seems to be no coherent plan for infrastructure delivery – a key component of the plan given the allocations being proposed near the already crowded Junction 7.
  • There seems to have been little or no cooperation with neighbouring boroughs or even parish councils within Swale itself.

The removal of a second consultation might have been understandable if this final version of the plan were similar to that being talked about at the beginning of the consultation process. It is, however, radically different in the following ways:

  • There has been a major shift in the balance of housing allocations, away from the west of the borough over to the east, especially around the historic town of Faversham. This is a move that raises many concerns.
  • A new large allocation, with accompanying A2 bypass, has appeared around Teynham and Lynsted, to which we are objecting.
  • Housing allocations in the AONB around Neames Forstal that were judged “unsuitable” by the council’s own officers have now appeared as part of the housing numbers.
  • Most of the housing allocations being proposed are on greenfield sites, many of them on Grade 1 agricultural land – a point to which we are strongly objecting.

Concerns about the rush to submit the plan

The haste with which the plan is being prepared is especially worrying given the concentration of housing in Faversham. If the town is to take a large amount of new housing, it is imperative that the policies concerning the area are carefully worked out to preserve, as far as possible, the unique nature of the town. The rush to submit the plan is likely to prove detrimental.

As Swale does not have a five-year land housing supply, it is open to speculative development proposals, many of which would run counter to the ideas contained in the current plan. Some are already appearing. This is a common situation, and one that, doubtless, is a reason behind Swale’s haste.

Our overriding fear, however, is that this emphasis on haste is ultimately going to prove counterproductive. This is because it is our view that the plan, in its current form, is unlikely to pass independent examination. We are urging Swale to listen to and act upon the comments being made about the plan and to return the plan to the council with appropriate modifications before submitting it to the Secretary of State.

Essentially, this means treating the current consultation not as the final one but as the ‘lost’ second consultation.

The consultation ends on Friday 30 April and we strongly urge residents to make their opinions known if they have not already done so.