High Court challenge puts Lower Thames Crossing in the spotlight
The future of the proposed Lower Thames Crossing was highlighted this week (Tuesday and Wednesday, June 29-30) when a legal challenge against the government’s roadbuilding programme was heard in the High Court.
The challenge was brought by the Transport Action Network and targeted the Department for Transport’s £27.4 billion roadbuilding scheme (labelled Road Investment Strategy 2, or RIS2), saying it breached climate and air quality laws.
TAN claims the government has failing to consider fully the Paris Agreement, which commits the UK to tackling climate change by limiting global warming to less than 2°C. Indeed, the group says the transport secretary pulled plans to cut CO2 emissions for a tranche of upgrades and new schemes.
RIS2 includes 50 schemes, the largest of which is the £8.2bn Lower Thames Crossing.
TAN said it expected the DfT to contest its challenge, saying commitments to climate change were not “obviously material” to roadbuilding schemes.
However, Chris Todd, TAN director, said: “Trying to argue climate change isn’t ‘obviously material’ to approving the largest-ever roads programme is like saying public health is not relevant to reform of smoking rules.
“In an audacious attempt to protect his addiction to asphalt, [Transport Secretary Grant ] Shapps is now seeking a legal precedent that decision-makers can ignore climate targets.
“This puts ministers on a collision course with the Climate Change Committee, which [has] called on the government to adopt a Net Zero Test for all policy decisions.”
Laura Blake, chairman of the Thames Crossing Action Group, said: “We know that the proposed Lower Thames Crossing would create over five million tonnes of carbon emissions, along with all the other negative impacts which we would suffer if the LTC were to go ahead.
“We have many serious concerns about the impacts of the proposed Lower Thames Crossing and feel it is essential that all the negative impacts of the scheme should be taken into account.
“We are grateful to TAN for bringing this legal challenge on climate grounds against the government’s £27bn roadbuilding programme, which of course includes the £8.2bn Lower Thames Crossing.
“We wholeheartedly support this legal challenge and appreciate all the hard work by TAN and the legal team.”
- For more on the Lower Thames Crossing, click here
- Transport Action Network has set up a ‘Stop the largest ever road-building programme’ CrowdJustice page
Thursday, July 1, 2021
- A number of important documents have yet to emerge. For example, a rigorous transport plan and a finalised air-quality assessment. The latter is critical given that allocations at Teynham will feed extra traffic into AQMAs.
- There seems to be no coherent plan for infrastructure delivery – a key component of the plan given the allocations being proposed near the already crowded Junction 7.
- There seems to have been little or no cooperation with neighbouring boroughs or even parish councils within Swale itself.
The removal of a second consultation might have been understandable if this final version of the plan were similar to that being talked about at the beginning of the consultation process. It is, however, radically different in the following ways:
- There has been a major shift in the balance of housing allocations, away from the west of the borough over to the east, especially around the historic town of Faversham. This is a move that raises many concerns.
- A new large allocation, with accompanying A2 bypass, has appeared around Teynham and Lynsted, to which we are objecting.
- Housing allocations in the AONB around Neames Forstal that were judged “unsuitable” by the council’s own officers have now appeared as part of the housing numbers.
- Most of the housing allocations being proposed are on greenfield sites, many of them on Grade 1 agricultural land – a point to which we are strongly objecting.
Concerns about the rush to submit the plan
The haste with which the plan is being prepared is especially worrying given the concentration of housing in Faversham. If the town is to take a large amount of new housing, it is imperative that the policies concerning the area are carefully worked out to preserve, as far as possible, the unique nature of the town. The rush to submit the plan is likely to prove detrimental.
As Swale does not have a five-year land housing supply, it is open to speculative development proposals, many of which would run counter to the ideas contained in the current plan. Some are already appearing. This is a common situation, and one that, doubtless, is a reason behind Swale’s haste.
Our overriding fear, however, is that this emphasis on haste is ultimately going to prove counterproductive. This is because it is our view that the plan, in its current form, is unlikely to pass independent examination. We are urging Swale to listen to and act upon the comments being made about the plan and to return the plan to the council with appropriate modifications before submitting it to the Secretary of State.
Essentially, this means treating the current consultation not as the final one but as the ‘lost’ second consultation.
The consultation ends on Friday 30 April and we strongly urge residents to make their opinions known if they have not already done so.
Further information