Charing public inquiry takes a break until April
It’s time for a breather at the public inquiry into Gladman Developments Ltd’s appeal against Ashford Borough Council’s refusal to grant planning permission for 245 homes at Pluckley Road in Charing.
CPRE Kent has been giving evidence at the inquiry, but today (Wednesday, March 28) was the last session before the break, with tomorrow’s planned site visit postponed.
The visit should now take place in the over-run week of Tuesday to Friday, April 24-27.
Today’s events at Ashford Civic Centre were devoted to a cross-examination and re-examination of Gladman’s witness over the council’s housing figures and whether the local authority can show it has enough housing in the pipeline to satisfy the five-year supply test.
Points raised by CPRE Kent in its evidence included:
- The appeal site is outside the village envelope and disconnected from the village centre
- Few people in Charing use the village train station to get to work, questioning the scheme’s sustainability
- Increased vehicle movements and the attendant risk to both drivers and pedestrians, including children coming home from school
- The setting of the village on the edge of the Kent Downs AONB
- The importance of the countryside in promoting health
- The planned development would add an unsustainable 30% to the village population
- The site is in a flood zone so could be flooded
- The risk of contamination to boreholes providing water to local people
In his opening statement, CPRE Kent’s Richard Knox-Johnston said: “The site of this appeal is a large open and rural field to the south of and distant from the Charing village envelope.
“This application by Gladman is speculative and is typical of applications they have made throughout the country, as described very clearly in the BBC One programme Countryfile, where the appellant [Gladman] declined to be interviewed.
“The comment in this programme was that these speculative applications were at the expense of local communities on a no-win no-fee basis.
“Gladman are not developers themselves, they are speculators and, having gained planning permission, will sell it on to a developer at a considerable profit. They make serious profits out of this fault line in the planning system.
“They specialise, as in this case, in submitting development applications on land that is not being considered in the draft Local Plan. Having then gained permission, either through a planning appeal, such as this, or through a High Court case, if the appeal is dismissed, they sell on to a developer or retain the option by land-banking, so increasing the value of the land.
“Selling on to a developer takes time. When a developer buys the permission they then, more often than not, ask for a viability assessment.
“This means renegotiating the original permission and conditions in order to ensure a minimum 20% profit margin.
“This also lengthens the time and causes further delay. Even if this appeal was to be successful, there would be a considerable delay in completing the development.
“It would therefore, in all likelihood, not assist with the five-year housing supply in Ashford.”
Wednesday, March 28, 2018
- A number of important documents have yet to emerge. For example, a rigorous transport plan and a finalised air-quality assessment. The latter is critical given that allocations at Teynham will feed extra traffic into AQMAs.
- There seems to be no coherent plan for infrastructure delivery – a key component of the plan given the allocations being proposed near the already crowded Junction 7.
- There seems to have been little or no cooperation with neighbouring boroughs or even parish councils within Swale itself.
The removal of a second consultation might have been understandable if this final version of the plan were similar to that being talked about at the beginning of the consultation process. It is, however, radically different in the following ways:
- There has been a major shift in the balance of housing allocations, away from the west of the borough over to the east, especially around the historic town of Faversham. This is a move that raises many concerns.
- A new large allocation, with accompanying A2 bypass, has appeared around Teynham and Lynsted, to which we are objecting.
- Housing allocations in the AONB around Neames Forstal that were judged “unsuitable” by the council’s own officers have now appeared as part of the housing numbers.
- Most of the housing allocations being proposed are on greenfield sites, many of them on Grade 1 agricultural land – a point to which we are strongly objecting.
Concerns about the rush to submit the plan
The haste with which the plan is being prepared is especially worrying given the concentration of housing in Faversham. If the town is to take a large amount of new housing, it is imperative that the policies concerning the area are carefully worked out to preserve, as far as possible, the unique nature of the town. The rush to submit the plan is likely to prove detrimental.
As Swale does not have a five-year land housing supply, it is open to speculative development proposals, many of which would run counter to the ideas contained in the current plan. Some are already appearing. This is a common situation, and one that, doubtless, is a reason behind Swale’s haste.
Our overriding fear, however, is that this emphasis on haste is ultimately going to prove counterproductive. This is because it is our view that the plan, in its current form, is unlikely to pass independent examination. We are urging Swale to listen to and act upon the comments being made about the plan and to return the plan to the council with appropriate modifications before submitting it to the Secretary of State.
Essentially, this means treating the current consultation not as the final one but as the ‘lost’ second consultation.
The consultation ends on Friday 30 April and we strongly urge residents to make their opinions known if they have not already done so.
Further information